Alphateam was approached by MPS to set up an automated alarm system for the Muja Switchyard. This system was crucial to the power station’s ability to function, with the alarms needing to be monitored by unit controllers at all times, as well as being able to run autonomously without fail.
Alphateam provided full configuration and commissioning of the switchyard alarm network, integrating it into the larger DCS via a communications protocol converter to give MPS complete oversight and control over their installed equipment.